Capped Alabama coal ash pond still polluting groundwater 7 years after closure, lawsuit claims
This article originally appeared on Inside Climate News, a nonprofit, independent news organization that covers climate, energy and the environment. It is republished with permission. Sign up for their newsletter here.
By Dennis Pillion, Inside Climate News
GADSDEN, Ala.—The coal ash lagoon at Alabama Power’s Plant Gadsden was supposed to be a model for how to close ash ponds by covering them in place, a process utilities insisted would protect human health and the environment from toxic contaminants in the ash.
Now, groundwater monitoring data and a federal lawsuit are challenging that contention.
The ash pond was the first in Alabama to be closed with a cover-in-place system in 2018, after the U.S. Environmental Protection Agency’s 2015 coal ash rules, and Alabama Power planned to use the same basic technique at the coal ash ponds for five other power plants across the state.
But today, seven years after the Gadsden pond closure was completed, environmental groups say the facility is still leaking toxic substances into groundwater on the banks of the Coosa River and Neely Henry Lake, a popular boating and bass fishing destination in east Alabama.
The Southern Environmental Law Center, on behalf of environmental group Coosa Riverkeeper, filed a lawsuit Tuesday against Alabama Power, challenging what it called “unlawful and defective capping” of the coal ash pond at Plant Gadsden.
The groups say that as recently as October 2024, Alabama Power’s self-reported groundwater monitoring results show “levels of arsenic forty times the legal standard in groundwater,” as well as potentially harmful levels of boron, chromium and cobalt.
“The citizens of Gadsden and folks who depend on Neely Henry Lake deserve so much better than Alabama Power’s legacy of pollution,” Justinn Overton, executive director and riverkeeper at Coosa Riverkeeper, said in a news release. “Drinking water supply, booming ecotourism, and hard-working Alabamians are all threatened by Alabama Power’s recklessness.”
Coosa Riverkeeper is among numerous groups that have called for Alabama Power to excavate its coal ash and move the material to a lined landfill, rather than leaving the ash in unlined impoundments near rivers. Alabama Power has announced plans to cap all of its coal ash ponds in place, but Gadsden is the only plant where that process has been completed.
“It’s time for Alabama Power to do the right thing and move their ash,” Overton said.
A spokesperson for Alabama Power said “[a]s a matter of practice, we do not comment on pending legal matters.”
Coal ash, or coal combustion residuals, are the leftover solid material from burning coal, typically in a power plant or other industrial facility. According to the EPA, coal ash often contains contaminants like mercury, cadmium, chromium and arsenic which can be “associated with cancer and various other serious health effects.”
The EPA’s 2015 coal ash rules allowed for two possible cleanup options for the coal ash lagoons, which can be hundreds of acres in size, containing millions of tons of wet ash slurry. Utilities could dig out the coal ash and move it to a lined landfill, or they could cover it in place, as long as certain conditions were met.
In 2016, Alabama Power announced plans to use the cover-in-place option at all its plants. The permit for Plant Gadsden was approved by the Alabama Department of Environmental Management in 2020, two years after the physical work had already been completed.
But last year, the EPA denied approval of Alabama’s coal ash permitting program, saying that the state had approved permits that were “significantly less protective of people and waterways than federal law requires,” and that “coal ash units cannot be closed in a way that allows coal ash to continue to spread contamination in groundwater after closure.”
The Riverkeeper lawsuit—filed in the U.S. District Court for the Northern District of Alabama—contends that nearly 40 percent of the ash at Gadsden remains saturated in groundwater, constituting a violation of the EPA coal ash rules and the Resource Conservation and Recovery Act.
It is not yet clear how the coal ash regulations will fare under the Trump administration.
The groups filed a notice of intent to sue in May, and went forward with the suit Tuesday, after the required 60-day notification period.
In addition to the lake being a popular fishing spot, the ash pond is located less than a mile upstream of a drinking water intake, although the lawsuit does not allege any contamination of the drinking water.
The coal ash pond at Plant Gadsden is on the opposite side of the river from the old power plant, which was demolished last year. According to the lawsuit, the coal ash slurry was pumped through underwater pipes across the river for disposal in a lagoon.
“There is no excuse for a company with Alabama Power’s resources to risk a community and commercial riverfront with this type of hazard,” Barry Brock, director of SELC’s Alabama office, said in a news release. “Alabama Power must join utilities across the South cleaning up unlined coal ash dumps. This type of waste must be in safe storage away from waterways like the Coosa and Neely Henry Lake.”
Auburn tabs USF’s Alex Golesh as its next coach, replacing Hugh Freeze on the Plains
The 41-year-old Golesh, who was born in Russia and moved to the United State at age 7, is signing a six-year contract that averages more than $7 million annually to replace Hugh Freeze. Freeze was fired in early November after failing to fix Auburn’s offensive issues in three seasons on the Plains.
Alabama Power seeks to delay rate hike for new gas plant amid outcry
The state’s largest utility has proposed delaying the rate increase from its purchase of a $622 million natural gas plant until 2028.
Former U.S. Sen. Doug Jones announces run for Alabama governor
Jones announced his campaign Monday afternoon, hours after filing campaign paperwork with the Secretary of State's Office. His gubernatorial bid could set up a rematch with U.S. Sen. Tommy Tuberville, the Republican who defeated Jones in 2020 and is now running for governor.
Scorching Saturdays: The rising heat threat inside football stadiums
Excessive heat and more frequent medical incidents in Southern college football stadiums could be a warning sign for universities across the country.
The Gulf States Newsroom is hiring an Audio Editor
The Gulf States Newsroom is hiring an Audio Editor to join our award-winning team covering important regional stories across Mississippi, Alabama and Louisiana.
Judge orders new Alabama Senate map after ruling found racial gerrymandering
U.S. District Judge Anna Manasco, appointed by President Donald Trump during his first term, issued the ruling Monday putting a new court-selected map in place for the 2026 and 2030 elections.